Roads23HF0107

CONCRETING OF BRGY. CABASIANGAN, BALAMBAN LEADING TO BRGY. TAGBAO, CEBU CITY FMR, BRGY. CABASIANGAN, BALAMBAN, CEBU

CONCRETING OF BRGY. CABASIANGAN, BALAMBAN LEADING TO BRGY. TAGBAO, CEBU CITY FMR, BRGY. CABASIANGAN, BALAMBAN, CEBU is a DPWH-tracked public work in Cebu 3rd DEO, Region VII. Reported contract value: ₱12,893,734.00. Status: Reported complete (DPWH). Contractor on record: HELM CONST. Figures trace to dpwh.

Cebu 3rd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Mitigation Structure at Combado River, Barangay Cantuod, Balamban, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

47 projects · ₱899.7M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTU

Cebu 3rd DEO, Region VII

2025₱95.9M
Past target date (DPWH On-Going)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY BASAK SAN NICOLAS, CEBU CITY

Cebu City DEO, Region VII

2023₱86.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SUBANGDAKU RIVER, CEBU CITY

Region VII, Region VII

2024₱67.5M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - SUBANGDAKU BR. (B00476CB) ALONG CEBU NORTH RD, CEBU CITY, CEBU

Cebu City DEO, Region VII

2025₱60.4M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS, LUYANG - POO - LAZI ROAD - K0022+840 - K0023+000, LAZI, SIQUIJOR

Siquijor DEO, Negros Island Region

2023₱49.0M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG GUADALUPE RIVER, BAR

Cebu City DEO, Region VII

2024₱48.9M
Reported complete (100% progress, DPWH status On-Going)
View all 47 projects →

4. Implementation

Contract Amount

₱12,893,734.00

Progress

Reported complete (DPWH)

Start Date

October 26, 2023

Target End

January 18, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.