Water Provision and Storage21EH0122

CONSTRUCTION OF 12 RAINWATER COLLECTOR SYSTEM (RWCS), SIBUYAN ISLAND, ROMBLON

CONSTRUCTION OF 12 RAINWATER COLLECTOR SYSTEM (RWCS), SIBUYAN ISLAND, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱4,350,557.51. Status: Reported complete (DPWH). Contractor on record: E K CO CONST. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Follow the peso

3 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2021 · ₱20,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱4,350,558 · E.K. CONSTRUCTION AND SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-05-02 → 2020-05-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF 12 RAINWATER COLLECTOR SYSTEM (RWCS), SIBUYAN ISLAND, ROMBLON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Campalingo Flood Control Structure along Sibuyan Circumferential Road, Sibuyan Island, Romblon
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Romblon DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Rainwater Collector System

₱4,350,557.51 · E.K. CONSTRUCTION AND SUPPLY

Award / contract ref: 21EH0122

Contractor

B

24 projects · ₱151.3M total · 0 flags

Other projects by this contractor

View all 24 projects →

4. Implementation

Contract Amount

₱4,350,557.51

Progress

Reported complete (DPWH)

Start Date

December 16, 2022

Target End

January 14, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
MIMAROPA RegionRomblonSan FernandoAzarga
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.