Buildings and Facilities16DN0108

CONSTRUCTION OF TWO (2) UNITS, FOUR (4) STOREY, TWENTY (20) CLASSROOM SCHOOL BUILDING, STAND ALONE SHS 8, TAYTAY, RIZAL

CONSTRUCTION OF TWO (2) UNITS, FOUR (4) STOREY, TWENTY (20) CLASSROOM SCHOOL BUILDING, STAND ALONE SHS 8, TAYTAY, RIZAL is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱60,318,487.08. Status: Reported complete (DPWH). Contractor on record: D R ROBLES CONST. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 78%

UACS
18001
Amount
₱8,512,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Rehabilitation of Flood Mitigation Facilities of Principal River along Upper Marikina River, Rodriguez River, Brgy. San Rafael, Rodriguez (Montalban), Rizal
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-16-0038824

₱90,245.00 · FY2016

Released to Adiong Memo (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱60,318,487.08

Progress

Reported complete (DPWH)

Start Date

December 19, 2017

Target End

November 13, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.