Roads22FC0221

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, DAANG MAHARLIKA (LZ) - K0366+318 - K0366+378, K0366+840 - K0366+954, K0367+970 - K0368+020, K0368+610 - K0368+648, K0368+792 - K0368+846, K0368+900 - K0368+9

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS, DAANG MAHARLIKA (LZ) - K0366+318 - K0366+378, K0366+840 - K0366+954, K0367+970 - K0368+020, K0368+610 - K0368+648, K0368+792 - K0368+846, K0368+900 - K0368+9 is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱48,929,917.40. Status: Reported complete (DPWH). Contractor on record: WIZARD CONCRETE SOLUTIONS AND CONST CORP FORMERLY: WIZARD TRADING & CONST. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱24,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control River in Barangay Dalas, Labo, Camarines Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Camarines Norte DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

38 projects · ₱1.9B total · 3 flags

4. Implementation

Contract Amount

₱48,929,917.40

Progress

Reported complete (DPWH)

Start Date

March 25, 2022

Target End

March 14, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.