Bridges22GF0058

REHABILITATION OF GUIMBAL STEEL BRIDGE, GUIMBAL, ILOILO

REHABILITATION OF GUIMBAL STEEL BRIDGE, GUIMBAL, ILOILO is a DPWH-tracked public work in Iloilo 1st DEO, Region VI. Reported contract value: ₱14,759,847.52. Status: Reported complete (DPWH). Contractor on record: NOE'S BUILDERS. Figures trace to dpwh.

Iloilo 1st DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Anonoo-Partition River Flood Control Project, Guimbal, Iloilo
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Iloilo 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,759,847.52

Progress

Reported complete (DPWH)

Start Date

August 22, 2022

Target End

April 5, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.