Roads25GI0040

OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS - MANDURRIAO-SN MIGUEL- ALIMODIAN-MAASIN-CABATUAN RD - K0023 + 089 - K0023 + 860

OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS - MANDURRIAO-SN MIGUEL- ALIMODIAN-MAASIN-CABATUAN RD - K0023 + 089 - K0023 + 860 is a DPWH-tracked public work in Iloilo 4th DEO, Region VI. Reported contract value: ₱34,624,491.00. Status: Past target date (DPWH On-Going). Contractor on record: 1 BEATUS BUILDERS CORP. Figures trace to dpwh.

Iloilo 4th DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Aganan Flood Control Structure Jaro-Aganan River), Barangay 6, San Miguel, Iloilo
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Iloilo 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱34,624,491.00

Progress

Past target date (DPWH On-Going)

Start Date

March 25, 2025

Target End

September 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.