Buildings and Facilities23AA0481

CONSTRUCTION OF CLASSROOMS, BATCH 1, 2 STY 8 CL, DAVILA ES, PASUQUIN, ILOCOS NORTE

CONSTRUCTION OF CLASSROOMS, BATCH 1, 2 STY 8 CL, DAVILA ES, PASUQUIN, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱23,999,968.90. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: IGWT-JAV CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project (Niquet-Bungro Section), Pasuquin, Ilocos Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ilocos Norte 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

39 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG NAYOM RIVER, SEGMENT B, BARANGAY POTOL, INFANTA, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱94.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG NAYOM RIVER, SEGMENT A, BARANGAY POTOL, INFANTA, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱94.6M
Past target date (DPWH On-Going)
No sat.

CONS./MAINTENANCE OF FLOOD MITIGATIONSTRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OFFLOOD MITIGATING STRUCTURE ALONG PADSAN RIVERCONNECTING BARANGAY 6 TONOTON, PIDDIG, ILOCOS NORTEAND BARANGAY SAN MARCOS, SITIO CABULOAN, SARRAT, ILOCOSNORTE

Ilocos Norte 1st DEO, Region I

2024₱77.2M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BANK SLOPE ALONG BAYAMBANG RIVER, STA. 001+523.2 - STA. 002+033.2, BARANGAY BAYAMBANG, INFANTA, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱70.9M
Past target date (DPWH On-Going)
No sat.

SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LED STREET LIGHTS ALONG ALAMINOS-BOLINAO ROAD K0357+660-K0361+140, BOLINAO, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱70.9M
Past target date (DPWH On-Going)
No sat.

SPECIAL ROAD FUND-MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - INSTALLATION OF SOLAR LED STREET LIGHTS ALONG ALAMINOS-BOLINAO ROAD, K0354+180-K0357+660, BOLINAO, PANGASINAN

Pangasinan 1st DEO, Region I

2025₱70.9M
Past target date (DPWH On-Going)
View all 39 projects →

4. Implementation

Contract Amount

₱23,999,968.90

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

August 11, 2023

Target End

April 23, 2024