Roads24C00001

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS-NUEVA ECIJA-AURORA ROAD, PROVINCE OF AURORA

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS-NUEVA ECIJA-AURORA ROAD, PROVINCE OF AURORA is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱145,712,215.83. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ROCK-WBL CONST CORP FOR: ROCK-WBL CONST TRADING & SERVICES. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱145,712,215.83

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

November 4, 2024

Target End

July 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.