Buildings and Facilities17FC0382

CONST. OF TWO (2) STOREY FOUR (4) C/L (SCIENCE & ICT LAB) SAN PEDRO DOMINGO LLARENA HS, STA. ELANA C

CONST. OF TWO (2) STOREY FOUR (4) C/L (SCIENCE & ICT LAB) SAN PEDRO DOMINGO LLARENA HS, STA. ELANA C is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱21,241,451.06. Status: Reported complete (DPWH). Contractor on record: KARPA BUILDERS AND TRADING. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,402,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Danao River Flood Control Structure, Sta. 0+000 - Sta. 0+580 (R/S) and Sta. 0+210 - Sta. 0+580 (L/S), Brgys. Parang and Plaridel, Jose Panganiban, Camarines Norte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-17-0009159

₱86,116.00 · FY2017

Released to Division of Camarines Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱21,241,451.06

Progress

Reported complete (DPWH)

Start Date

January 14, 2018

Target End

July 4, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.