Buildings and Facilities20MA0092

REHABILITATION OF COVERED COURT AT POBLACION TUMBAO, MANGUDADATU, MAGUINDANAO

REHABILITATION OF COVERED COURT AT POBLACION TUMBAO, MANGUDADATU, MAGUINDANAO is a DPWH-tracked public work in Cotabato City DEO, Region XII. Reported contract value: ₱2,940,163.28. Status: Reported complete (DPWH). Contractor on record: RNS CONST ENGINEERING. Figures trace to dpwh.

Cotabato City DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construcion of Simuay Flood Control (River Bank Protection with Revetment), Sta.0+000-Sta.0+940, Sta.1+440-Sta.2+460, Macaguiling, Sultan Kudarat, Maguindanao
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Cotabato City DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

39 projects · ₱462.4M total · 0 flags

4. Implementation

Contract Amount

₱2,940,163.28

Progress

Reported complete (DPWH)

Start Date

October 22, 2020

Target End

January 29, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.