Buildings and Facilities18GH0005

CONSTRUCTION OF COVERED COURT, BRGY. SANTIAGO, BAROTAC VIEJO, ILOILO

CONSTRUCTION OF COVERED COURT, BRGY. SANTIAGO, BAROTAC VIEJO, ILOILO is a DPWH-tracked public work in Iloilo 3rd DEO, Region VI. Reported contract value: ₱1,974,810.14. Status: Reported complete (DPWH). Contractor on record: WINCES CONST. Figures trace to dpwh.

Iloilo 3rd DEO, Region VI
Region: Region VI

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱15,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROI-18-0007875 · ₱79,883 · release to the district office, not itemized per project

    Possible match · score 0.70

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18GH0005 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-04-01 → 2025-04-20

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF COVERED COURT, BRGY. SANTIAGO, BAROTAC VIEJO, ILOILO

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project, Barotac Viejo River Control, Brgy. Natividad, Barotac Viejo, Iloilo
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-18-0007875

₱79,883.00 · FY2018

Released to Regional Office - I (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,974,810.14

Progress

Reported complete (DPWH)

Start Date

February 9, 2018

Target End

April 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VI (Western Visayas)IloiloBarotac ViejoSantiago
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.