Construction of Flood Mitigation Structure24MF0048

Construction of Flood Control Structure along Ala River Purok Prinsipe, Kolambog, Sultan Kudarat.

Construction of Flood Control Structure along Ala River Purok Prinsipe, Kolambog, Sultan Kudarat. is a DPWH-tracked public work in ISULAN (CAPITAL) (SULTAN KUDARAT), SULTAN KUDARAT, Region XII. Reported contract value: ₱48,112,936.13. Status: Reported complete (DPWH). Contractor on record: KANAWAY BUILDERS CORP. Figures trace to sumbong.

ISULAN (CAPITAL) (SULTAN KUDARAT), SULTAN KUDARAT, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱46,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Ala River ( Bambad - Kalawag ) , Isulan, Sultan Kudarat
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-24-0007654

₱1,478,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROXII-24-0003834

₱139,989.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROXII-24-0007842

₱136,000.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,112,936.13

Progress

Reported complete (DPWH)

Start Date

May 15, 2024

Target End

December 2, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.