Construction of Slope Protection Structure21CL0091

Construction/Rehabilitation/Improvement of Slope Protection along Olongapo - Bugallon Road, Pangolingan Section (Phase 2), Palauig, Zambales

Construction/Rehabilitation/Improvement of Slope Protection along Olongapo - Bugallon Road, Pangolingan Section (Phase 2), Palauig, Zambales is a DPWH-tracked public work in ZAMBALES, Region III. Reported contract value: ₱46,794,299.56. Status: Reported complete (DPWH). Contractor on record: STO CRISTO CONST & TRADING INC FOR: STO CRISTO CONST & TRADING. Figures trace to sumbong.

ZAMBALES, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱1,872,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of slope protection/flood control along Bancal River (Cabatuhan Phase 2), Botolan, Zambales (Upstream)
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014127

₱66,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012571

₱30,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013836

₱7,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-21-0000276

₱621,023.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

View all 55 projects →

4. Implementation

Contract Amount

₱46,794,299.56

Progress

Reported complete (DPWH)

Start Date

April 27, 2022

Target End

November 22, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.