Buildings and Facilities25MF0030

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) BARANGAY TAYUGO, ISULAN,SULTAN KUDARAT

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) BARANGAY TAYUGO, ISULAN,SULTAN KUDARAT is a DPWH-tracked public work in Sultan Kudarat 1st DEO, Region XII. Reported contract value: ₱4,944,580.03. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: FPJ CONST AND SUPPLY. Figures trace to dpwh.

Sultan Kudarat 1st DEO, Region XII
Region: Region XII

Follow the peso

2 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱5,000

    Possible match · score 0.65

    DBM GAA source ↗
  2. 2. SARO / NCA release

    Not yet linked

  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-11-26 → 2025-04-02

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) BARANGAY TAYUGO, ISULAN,SULTAN KUDARAT

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 65%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Multi-Purpose Building (Barangay Hall) Barangay Tayugo, Isulan, Sultan Kudarat
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Sultan Kudarat 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,944,580.03

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 17, 2025

Target End

August 8, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.