Roads22CA0076

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. GUGO, SAMAL, BATAAN

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. GUGO, SAMAL, BATAAN is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱4,949,997.94. Status: Reported complete (DPWH). Contractor on record: M C J VALENZUELA CONST ENT. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project along Sapa Creek, Barangay Sapa, Samal, Bataan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Bataan 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

22CA0076 - Construction Project

₱4,850,997.97 · M.C.J. VALENZUELA CONSTRUCTION ENTERPRISES

Contractor

A

58 projects · ₱1.9B total · 27 flags

4. Implementation

Contract Amount

₱4,949,997.94

Progress

Reported complete (DPWH)

Start Date

September 1, 2022

Target End

February 27, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.