Roads16CK0073

CONST/IMPT OF ACCESS RDS LEADING TO AIRPORTS, SEAPORTS & TOURIST DEST-CONST OF A NEW CLARKGREEN

CONST/IMPT OF ACCESS RDS LEADING TO AIRPORTS, SEAPORTS & TOURIST DEST-CONST OF A NEW CLARKGREEN is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱184,280,446.65. Status: Reported complete (DPWH). Contractor on record: LEADWAY CONST. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-16-0038894

₱5,140,000.00 · FY2016

Released to Culion Sani (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

27 projects · ₱3.2B total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT PROGRAM; CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES/LONG SPAN BRIDGES; CUTCUT FLYOVER ALONG FRIENDSHIP CIRCUM RD. PAMPANGA

Pampanga 3rd DEO, Region III

2023₱289.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS-TO DECLARED TOURISM DESTINATIONS, CLARK GREEN CITY-MAC ARTHUR ACCESS ROAD LEADING TO CLARK GREEN CITY, INCLUDING BRIDGES, TARLAC 3RD L.D. PROV. OF TAR

Region III, Region III

2017₱233.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM-REPLACEMENT OF PERMANENT WEAK BRIDGES, CHICO KARAYAN BR. (B00924LZ) ALONG MT. PROVINCE - NUEVA VIZCAYA RD.

Cordillera Administrative Region, Cordillera Administrative Region

2018₱208.3M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS, CAPAS-BOTOLAN ROAD-PACKAGE 3, PROVINCE OF ZAMBALES

Region III, Region III

2024₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS, AND DECLARED TOURISM DESTINATION CONSTRUCTION OF CONCRETE BRIDGE POBLACION-LAPPA-MARAG ROAD LEADING TO MARAG VALLEY (BRIDGE CONSTRUCTION - PHASE 1), LUNA, APAYAO

Cordillera Administrative Region, Cordillera Administrative Region

2017₱173.4M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS, BACOLOR-PORAC ACCESS ROAD (PORAC SECTION)-PACKAGE 1, PROVINCE OF PAMPANGA

Region III, Region III

2023₱172.1M
Past target date (DPWH On-Going)
View all 27 projects →

4. Implementation

Contract Amount

₱184,280,446.65

Progress

Reported complete (DPWH)

Start Date

October 20, 2016

Target End

October 4, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.