Buildings and Facilities21OD0130

CONSTRUCTION (COMPLETION) OF PAMANTASAN NG LUNGSOD NG VALENZUELA (SATELLITE BUILDING), BARANGAY MALINTA, VALENZUELA CITY

CONSTRUCTION (COMPLETION) OF PAMANTASAN NG LUNGSOD NG VALENZUELA (SATELLITE BUILDING), BARANGAY MALINTA, VALENZUELA CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱148,727,315.46. Status: Reported complete (DPWH). Contractor on record: J SIMEON CONST 31867. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along De Castro (Phase III), Barangay Paso De Blas, Valenzuela City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Metro Manila 3rd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱148,727,315.46

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

March 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.