Buildings and Facilities19HN0087

CONSTRUCTION OF 1-STOREY, 2-CLASSROOM SCHOOL BUILDING AT POLOG ES, CONSOLACION, CEBU

CONSTRUCTION OF 1-STOREY, 2-CLASSROOM SCHOOL BUILDING AT POLOG ES, CONSOLACION, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱0.00. Status: Past target date (DPWH On-Going). Contractor on record: GREEN WORLD CONST. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    NCA NCA-CAR-19-0010230 · ₱897,498 · release to the district office, not itemized per project

    Possible match · score 0.66

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19HN0087 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    0% reported · imagery 2018-03-17 → 2026-02-04

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF 1-STOREY, 2-CLASSROOM SCHOOL BUILDING AT POLOG ES, CONSOLACION, CEBU

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-CAR-19-0010230

₱897,498.00 · FY2019

Released to Nueva Vizcaya District Engineering Offi Baguio General Hospital and Medical Cen (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

45 projects · ₱594.8M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP): CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS, WATER SUPPLY SYSTEMS: CONSTRUCTION OF LEVEL III WATER SUPPLY SYSTEM, DUMANJUG, CEBU

Cebu 7th DEO, Region VII

2023₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT PUROK MAIS-PUROK NANGKA (PACKAGE

Cebu 7th DEO, Region VII

2024₱94.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF REVETMENT WALL AT PUROK MAIS - PUROK NANGKA, BARAN

Cebu 7th DEO, Region VII

2024₱70.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL ALONG LALAO RIVER (UPSTREAM), MALABUYOC, CEBU

Cebu 7th DEO, Region VII

2025₱56.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAINWATER COLLECTORS - WATER SUPPLY SYSTEM - CONSTRUCTION OF LOON - CABILAO WATERWORKS, LOON, BOHOL

Bohol 1st DEO, Region VII

2023₱48.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM: CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, WATER MANAGEMENT FACILITIES/WATER SUPPLY, CONSTRUCTION OF WATER SUPPLY PROJECT, ARGAO, CEBU

Cebu 2nd DEO, Region VII

2018₱41.0M
Reported complete (DPWH)
View all 45 projects →

4. Implementation

Contract Amount

₱0.00

Progress

Past target date (DPWH On-Going)

Start Date

October 15, 2019

Target End

February 6, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)CebuConsolacionPolog
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.