Bridges17CF0165

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL BRIDGES, CONSTRUCTION OF RIO CHICO BRIDGE LEADING TO SITIO PANTAY AND BIGNAY, RIO CHICO, GENERAL TINIO, NUEVA ECIJA, STA. 0+000.00 -STA. 0+422.80

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL BRIDGES, CONSTRUCTION OF RIO CHICO BRIDGE LEADING TO SITIO PANTAY AND BIGNAY, RIO CHICO, GENERAL TINIO, NUEVA ECIJA, STA. 0+000.00 -STA. 0+422.80 is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱82,390,179.04. Status: Reported complete (DPWH). Contractor on record: REBCOR CONST AND TRADING CORP. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱8,336,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Coronel River, Calabasa, Sta. 20+898.25-Sta. 20+981.30, Gabaldon, Nueva Ecija
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0015657

₱32,557.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱82,390,179.04

Progress

Reported complete (DPWH)

Start Date

October 25, 2017

Target End

August 20, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.