Construction of Revetment24OC0118

Construction of Flood Mitigation Structure along Villanueva Creek, Parañaque City

Construction of Flood Mitigation Structure along Villanueva Creek, Parañaque City is a DPWH-tracked public work in CITY OF PARAÑAQUE (METROPOLITAN MANILA), PARAÑAQUE CITY, National Capital Region. Reported contract value: ₱79,048,492.76. Status: Reported complete (DPWH). Contractor on record: E R RODRIGUEZ CONST CORP FORMERLY: E R RODRIGUEZ CONST. Figures trace to sumbong.

CITY OF PARAÑAQUE (METROPOLITAN MANILA), PARAÑAQUE CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure ( Installation of Trash Screen ) along Bangkal Creek, Makati City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0016746

₱30,000,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008744

₱1,531,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0003336

₱309,005.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008761

₱141,000.00 · FY2024

Source

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Flood Mitigation Structure

₱76,038,240.26 · E.R. RODRIGUEZ CONSTRUCTION

Contractor

41 projects · ₱1.9B total · 0 flags

4. Implementation

Contract Amount

₱79,048,492.76

Progress

Reported complete (DPWH)

Start Date

May 9, 2024

Target End

February 2, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.