CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY TALISAYAN (PACKAGE 1), ZAMBOANGA CITY

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY TALISAYAN (PACKAGE 1), ZAMBOANGA CITY is a DPWH-tracked public work in Zamboanga City 1st DEO, Region IX. Reported contract value: ₱19,244,591.04. Status: Reported complete (DPWH). Contractor on record: VICTER CONST AND DEVELOPMENT OPC. Figures trace to dpwh.

Zamboanga City 1st DEO, Region IX
Region: Region IX

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2024 · ₱5,000

    Probable match · score 0.90

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 24JK0001 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2024-10-29 → 2025-02-13

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BARANGAY TALISAYAN (PACKAGE 1), ZAMBOANGA CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure ( Drainage ) , Barangay Ayala, Zamboanga City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zamboanga City 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,244,591.04

Progress

Reported complete (DPWH)

Start Date

January 30, 2025

Target End

August 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IX (Zamboanga Peninsula)City of ZamboangaTalisayan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.