Buildings and Facilities19PD0137

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF MULTI-PURPOSE BUILDING (BASKETBALL COURT) AT PUROK 6, BARANGAY ASIN, BAGUIO CITY, BENGUET

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF MULTI-PURPOSE BUILDING (BASKETBALL COURT) AT PUROK 6, BARANGAY ASIN, BAGUIO CITY, BENGUET is a DPWH-tracked public work in Baguio City DEO, Cordillera Administrative Region. Reported contract value: ₱2,308,917.45. Status: Reported complete (DPWH). Contractor on record: BOYDROCK CONST. Figures trace to dpwh.

Baguio City DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-A-19-0026253

₱61,610.00 · FY2019

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

31 projects · ₱232.8M total · 0 flags

Other projects by this contractor

No sat.

CONTRACT PACKAGE 6: CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY (TIKAS) A) CONST (COMPLETION) OF HEADQUARTERS SUPPORT GROUP BUILDING, PMA, BAGUIO CITY B) CONST (COMPLETION) OF KILL HOUSE, PMA, BAGUIO CITY

Baguio City DEO, Cordillera Administrative Region

2022₱20.3M
Reported complete (DPWH)
No sat.

NATIONAL BUILDING PROGRAM-REHABILITATION OF NATIONAL BUREAU OF INVESTIGATION (NBI) BUILDING, BAGUIO CITY

Baguio City DEO, Cordillera Administrative Region

2022₱19.6M
Reported complete (DPWH)
No sat.

NATIONAL DISASTER RISK REDUCTION AND MANAGEMENT FUND (NDRRMF) (CALAMITY FUND) FLOOD CONTROL STRUCTURES: RESTORATION OF COLLAPSED REVETMENT WALL NEAR BALACBAC BRIDGE DAMAGED BY TY OMPONG

Baguio City DEO, Cordillera Administrative Region

2018₱18.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF TWO (2) STOREY BUILDING, DEPARTMENT OF JUSTICE (DOJ) SECRETARY'S COTTAGE, CABINET HILL, BAGUIO CITY

Baguio City DEO, Cordillera Administrative Region

2021₱17.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-MARCOS HI-WAY TO KENNON ROAD DIVERSION ROAD, BAGUIO CITY

Baguio City DEO, Cordillera Administrative Region

2021₱14.6M
Reported complete (DPWH)
No sat.

REH. OF DISASTER-REL. INFRA & OTHER FAC.-IMPLEM. OF CALAMITY-RELATED PROJS IN BAGUIO CITY W/C WERE DAMAGED BY TY VINTA, URDUJA, MARING, AMANG, HABAGAT, USMAN & OMPONG IN 2017 AND 2018: REST. OF ROADSLIP & OTHER REL. STRUCT ALONG BENGAO RD, BAGUIO CITY

Baguio City DEO, Cordillera Administrative Region

2019₱13.0M
Reported complete (DPWH)
View all 31 projects →

4. Implementation

Contract Amount

₱2,308,917.45

Progress

Reported complete (DPWH)

Start Date

January 4, 2021

Target End

May 23, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.