Roads20Z00012

MARAWI TRANSCENTRAL ROAD, PHASE III, UNDER ROAD NETWORK DEVELOPMENT PROJECT IN CONFLICT AFFECTED AREAS IN MINDANAO (RNDP-CAAM), JICA LOAN AGREEMENT NO. PH-F-P1, CONTRACT PACKAGE 3-D, REHABILITATION OF TRANSCENTRAL ROADS, MARAWI CITY, LANAO DEL SUR

MARAWI TRANSCENTRAL ROAD, PHASE III, UNDER ROAD NETWORK DEVELOPMENT PROJECT IN CONFLICT AFFECTED AREAS IN MINDANAO (RNDP-CAAM), JICA LOAN AGREEMENT NO. PH-F-P1, CONTRACT PACKAGE 3-D, REHABILITATION OF TRANSCENTRAL ROADS, MARAWI CITY, LANAO DEL SUR is a DPWH-tracked public work in Roads Management Cluster I (Bilateral), Central Office. Reported contract value: ₱173,152,437.15. Status: Reported complete (DPWH). Contractor on record: CDH CONST 37936. Figures trace to dpwh.

Roads Management Cluster I (Bilateral), Central Office
Region: Central Office

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱173,152,437.15

Progress

Reported complete (DPWH)

Start Date

May 14, 2021

Target End

December 22, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.