Flood Control and Drainage19K00050

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-KOLAMBOGAN FLOOD CONTROL PROJECT, KOLAMBOGAN, LANAO DEL NORTE

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE-KOLAMBOGAN FLOOD CONTROL PROJECT, KOLAMBOGAN, LANAO DEL NORTE is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱116,353,690.95. Status: Reported complete (DPWH). Contractor on record: CDH CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱116,353,690.95

Progress

Reported complete (DPWH)

Start Date

July 26, 2019

Target End

April 20, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.