Roads23C00008

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-TERTIARY ROADS, BALER CEMENTO VIA DICOLUYUNGAN ROAD, PROVINCE OF AURORA

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-TERTIARY ROADS, BALER CEMENTO VIA DICOLUYUNGAN ROAD, PROVINCE OF AURORA is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱302,932,793.23. Status: Reported complete (DPWH). Contractor on record: S-ANG CONST & GEN TRADING INC 37149. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 37149

21 projects · ₱2.9B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE-SECONDARY ROADS-MADELLA-DINADIAWAN ROAD, PROVINCE OF AURORA

Region III, Region III

2023₱347.1M
Past target date (DPWH On-Going)
No sat.

ACTIVE TRANSPORT BIKE SHARE SYSTEM AND SAFE PATHWAYS PROGRAM IN METROPOLITAN AREAS - MAINTENANCE AND UPGRADING OF ACTIVE TRANSPORT INFRASTRUCTURE PHASE II

National Capital Region, National Capital Region

2022₱146.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - REHABILITATION OF FLOOD CONTROL STRUCTURE, BARANGAY TAMOGONG, (BAIS BRI

Negros Oriental 2nd DEO, Negros Island Region

2025₱141.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CANLUMBOG RIVER, BAIS CITY, NE

Negros Oriental 2nd DEO, Negros Island Region

2025₱141.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BATANG RIVER, BARANGAY LUMBANG

Negros Oriental 2nd DEO, Negros Island Region

2025₱141.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DOWNSTREAM), BARANGAY LUYANG,

Negros Oriental 2nd DEO, Negros Island Region

2025₱141.1M
Past target date (DPWH On-Going)
View all 21 projects →

4. Implementation

Contract Amount

₱302,932,793.23

Progress

Reported complete (DPWH)

Start Date

August 21, 2023

Target End

August 14, 2024

5. Audit