Roads23BG0183

CSSP-BASIC INFRASTRUCTURE PROGRAM-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD WITH DRAINAGE CANAL OF MUNICIPAL GOVERNMENT CENTER PHASE 2, BRGY. NAPACCU PEQUENO, REINA MER

CSSP-BASIC INFRASTRUCTURE PROGRAM-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD WITH DRAINAGE CANAL OF MUNICIPAL GOVERNMENT CENTER PHASE 2, BRGY. NAPACCU PEQUENO, REINA MER is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱49,489,505.65. Status: Reported complete (DPWH). Contractor on record: DRAGON TWELVE BUILDERS. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cagayan River Flood Control Project, Brgy. District 1 (Sta. 0+000 - Sta. 0+550), Reina Mercedes, Isabela
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Isabela 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

448 projects · ₱5.8B total · 0 flags

Other projects by this contractor

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF BALLACAYU FLOOD CONTROL SYSTEM

Isabela 1st DEO, Region II

2024₱144.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AL

Isabela 1st DEO, Region II

2025₱144.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE

Isabela 1st DEO, Region II

2025₱144.7M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAGAYAN RIVER (PACKAGE

Isabela 1st DEO, Region II

2025₱140.4M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS- FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE

Isabela 1st DEO, Region II

2025₱96.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AL

Isabela 1st DEO, Region II

2025₱96.5M
Past target date (DPWH On-Going)
View all 448 projects →

4. Implementation

Contract Amount

₱49,489,505.65

Progress

Reported complete (DPWH)

Start Date

August 9, 2023

Target End

March 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.