WIDENING OF PERMANENT BRIDGES, BURABOD BR. 1 (B00303SM) ALONG CATARMAN - LAOANG RD., LAOANG, NORTHERN SAMAR

WIDENING OF PERMANENT BRIDGES, BURABOD BR. 1 (B00303SM) ALONG CATARMAN - LAOANG RD., LAOANG, NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 2nd DEO, Region VIII. Reported contract value: ₱14,958,918.45. Status: Reported complete (DPWH). Contractor on record: BCG DESIGN AND CONST. Figures trace to dpwh.

Northern Samar 2nd DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

20II0017, Widening of Permanent Bridges

₱14,959,268.86 · BCG DESIGN AND CONSTRUCTION

Contractor

68 projects · ₱621.6M total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0731+940, K0731+525 - K0732+087, SAMAR 1ST LD

Region VIII, Region VIII

2025₱28.9M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0715+000 - K0715+282, K0723+000 - K0723+586, K0724+579 - K0724+650

Region VIII, Region VIII

2024₱28.9M
Past target date (DPWH On-Going)
No sat.

OO1:PREVENTIVE MAINTENANCE - TERTIARY ROADS - CALBAYOG DIVERSION RD. K0736+306 - K0736+665.65, SAMAR

Samar 1st DEO, Region VIII

2024₱25.1M
Reported complete (DPWH)
No sat.

CSSP- SIPAG- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD, BRGY. POLANGI TO BRGY. LITERON, CALBIGA, SAMAR

Samar 2nd DEO, Region VIII

2025₱24.5M
Past target date (DPWH On-Going)
No sat.

CSSP- SIPAG- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-REHAB. OF ROAD, BARANGAY LOKILOKON, PARANAS TO BARANGAY HINICA-AN, MOTIONG, SAMAR, STA. 0+700-STA. 1+228, PARANAS, SAMAR

Samar 2nd DEO, Region VIII

2025₱24.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPARK SAMAR MULTI-PURPOSE TRAINING CENTER), BRGY. PAYAO, CATBALOGAN CITY, SAMAR

Samar 2nd DEO, Region VIII

2023₱24.3M
Reported complete (100% progress, DPWH status On-Going)
View all 68 projects →

4. Implementation

Contract Amount

₱14,958,918.45

Progress

Reported complete (DPWH)

Start Date

February 21, 2020

Target End

November 7, 2020

5. Audit