Buildings and Facilities17DD0256

CONSTRUCTION OF FOUR (4) STOREY SIXTEEN (16) CLASSROOMS SCHOOL BUILDING AT SAN JOSE ES, BRGY. SAN JOSE, LIPA CITY, BATANGAS

CONSTRUCTION OF FOUR (4) STOREY SIXTEEN (16) CLASSROOMS SCHOOL BUILDING AT SAN JOSE ES, BRGY. SAN JOSE, LIPA CITY, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱37,246,332.50. Status: Reported complete (DPWH). Contractor on record: URBAN CONSOLIDATED CONSTRUCTORS PHILS INC FOR U 5108. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱37,246,332.50

Progress

Reported complete (DPWH)

Start Date

December 17, 2017

Target End

September 12, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.