Buildings and Facilities19FJ0030

CONSTRUCTION OF DPWH MULTI-PURPOSE BUILDING AND OTHER FACILITIES, MASBATE 2ND DISTRICT ENGINEERING OFFICE COMPOUND, DIMASALANG, MASBATE

CONSTRUCTION OF DPWH MULTI-PURPOSE BUILDING AND OTHER FACILITIES, MASBATE 2ND DISTRICT ENGINEERING OFFICE COMPOUND, DIMASALANG, MASBATE is a DPWH-tracked public work in Masbate 3rd DEO, Region V. Reported contract value: ₱30,689,997.25. Status: Reported complete (DPWH). Contractor on record: URBAN CONSOLIDATED CONSTRUCTORS PHILS INC FOR U. Figures trace to dpwh.

Masbate 3rd DEO, Region V
Region: Region V

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    NCA NCA-ROII-19-0008997 · ₱33,537 · release to the district office, not itemized per project

    Possible match · score 0.69

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19FJ0030 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-01-18 → 2022-08-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF DPWH MULTI-PURPOSE BUILDING AND OTHER FACILITIES, MASBATE 2ND DISTRICT ENGINEERING OFFICE COMPOUND, DIMASALANG, MASBATE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROII-19-0008997

₱33,537.00 · FY2019

Released to Lamo National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱30,689,997.25

Progress

Reported complete (DPWH)

Start Date

July 3, 2019

Target End

April 27, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)MasbateDimasalangBalocawe
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.