GAA 2025 SSP25HC0071

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, BRGY LAPACAN SUR (INABANGA, BOHOL) TO BRGY PANG

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, BRGY LAPACAN SUR (INABANGA, BOHOL) TO BRGY PANG is a DPWH-tracked public work in Bohol 2nd DEO, Region VII. Reported contract value: ₱98,899,107.50. Status: Past target date (DPWH On-Going). Contractor on record: RL EARTH HAULING & EQUIPMENT SERVICES INC. Figures trace to dpwh.

Bohol 2nd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Protection Dike, Cahayag CIS, Tubigon, Bohol
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bohol 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

10 projects · ₱769.4M total · 0 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. RUFO HILL TO BARGU, BUENAVISTA, BOHOL

Bohol 2nd DEO, Region VII

2024₱99.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF TIGBAO CIRCUMFERENTIAL ROAD, TIGBAO, LOBOC, BOHOL

Bohol 3rd DEO, Region VII

2024₱98.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONSTRUCTION OF ROAD, BRGY. BATUAN TO BRGY OVERLAND, BUENAVISTA, BOHO

Bohol 2nd DEO, Region VII

2025₱98.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS: CONSTRUCTION OF DIVERSION ROAD, BRGY POBLACION TO BRGY FATIMA, UBAY, BOHOL

Bohol 2nd DEO, Region VII

2023₱97.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BRGY. UPPER BONBON TO BRGY. BUGHO, LOBOC, BOHOL

Bohol 3rd DEO, Region VII

2025₱96.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM- KATUPARAN)- ACCESS ROAD LEADING TO UBAY PORT VIA RECLAMATION AREA, UBAY, BOHOL

Bohol 2nd DEO, Region VII

2025₱79.6M
Past target date (DPWH On-Going)
View all 10 projects →

4. Implementation

Contract Amount

₱98,899,107.50

Progress

Past target date (DPWH On-Going)

Start Date

June 12, 2025

Target End

February 7, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.