Flood Control and Drainage18LB0040

CONST. OF CONC. REVETMENT OF STEEL SHEET PILES ALONG DAVAO RIVER,BOLTON BRIDGE DOWNSTREAM SECTION, R

CONST. OF CONC. REVETMENT OF STEEL SHEET PILES ALONG DAVAO RIVER,BOLTON BRIDGE DOWNSTREAM SECTION, R is a DPWH-tracked public work in Davao City DEO, Region XI. Reported contract value: ₱96,403,500.00. Status: Reported complete (DPWH). Contractor on record: DREIRICH BUILDERS. Figures trace to dpwh.

Davao City DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Concrete Revetment on Steel Sheet Piles along Talomo River, Calinan Section, Davao City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-LGRCB-18-0025292

₱50,900,000.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,403,500.00

Progress

Reported complete (DPWH)

Start Date

May 16, 2018

Target End

February 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.