Bridges16GI0027

RETROFFITING/STRENGTHENING OF VARIOUS PERMANENT BRIDGES A. AGANAN BR (NEW) (B00500PN) ILOILO-CAPIZ RD (OLD ROUTE) B. AGANAN BRIDGE (OLD) (B00046PN)ILOILO-CAPIZ RD (PAVIA DIVERSION) C. INGUAN BR (B00004PN) JCT. BANCAL-LEON-ANTIQUE D.TACUYONG BR (B00169PN)

RETROFFITING/STRENGTHENING OF VARIOUS PERMANENT BRIDGES A. AGANAN BR (NEW) (B00500PN) ILOILO-CAPIZ RD (OLD ROUTE) B. AGANAN BRIDGE (OLD) (B00046PN)ILOILO-CAPIZ RD (PAVIA DIVERSION) C. INGUAN BR (B00004PN) JCT. BANCAL-LEON-ANTIQUE D.TACUYONG BR (B00169PN) is a DPWH-tracked public work in Iloilo 4th DEO, Region VI. Reported contract value: ₱25,788,271.90. Status: Reported complete (DPWH). Contractor on record: EC STRUCTURAL COMPOSITES INC. Figures trace to dpwh.

Iloilo 4th DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Aganan Flood Control Project (Jaro - Aganan River), Poblacion, San Miguel, Iloilo 2nd LD
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0028783

₱9,561,000.00 · FY2016

Released to Naval State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱25,788,271.90

Progress

Reported complete (DPWH)

Start Date

April 7, 2016

Target End

September 13, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.