Roads17GI0162

CONSTRUCTION/OPENING OF BRGY. BOBON, LEON TO BRGY. MANASA, ALIMODIAN FMR, BRGY BOBON, LEON, ILOILO

CONSTRUCTION/OPENING OF BRGY. BOBON, LEON TO BRGY. MANASA, ALIMODIAN FMR, BRGY BOBON, LEON, ILOILO is a DPWH-tracked public work in Iloilo 4th DEO, Region VI. Reported contract value: ₱17,014,497.91. Status: Reported complete (DPWH). Contractor on record: PATRILA BUILDERS INC. Figures trace to dpwh.

Iloilo 4th DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Aganan Flood Control Project (Jaro-Aganan River), Brgy. 9 to Brgy 14, San Miguel, Iloilo
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-17-0024542

₱103,000.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱17,014,497.91

Progress

Reported complete (DPWH)

Start Date

January 12, 2018

Target End

August 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.