Buildings and Facilities21HD0018

REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ISIDRO, TABOGON, CEBU

REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ISIDRO, TABOGON, CEBU is a DPWH-tracked public work in Cebu 4th DEO, Region VII. Reported contract value: ₱1,000,000.00. Status: Reported complete (DPWH). Contractor on record: E V CABALLERO CONST. Figures trace to dpwh.

Cebu 4th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Dugo-an River Flood Control, Barangay Dugo-an, Dumanjug, Cebu
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Cebu 4th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

27 projects · ₱96.8M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CONCRETE BRIDGE, SITIO CAMPO,

Cebu City DEO, Region VII

2024₱14.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT PAMINTAO RIVER ALONG CEBU NORTH HAGNAYA WHARF ROAD, BARANGAY TAYTAYAN, CITY OF BOGO

Cebu 4th DEO, Region VII

2018₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, PACKAGE 2, BARANGAY LABA

Cebu City DEO, Region VII

2025₱9.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES-ROAD CONCRETING, BRGY. LABANGON, CEBU CITY, C

Cebu City DEO, Region VII

2023₱9.6M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. LABANGON, CEBU CITY

Cebu City DEO, Region VII

2020₱5.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF 2-UNITS UNIQUE WORKSHOP BUILDING, DOÑA LILING NEIS NEGAPATAN NHS, TABOGON, CEBU

Cebu 4th DEO, Region VII

2017₱5.2M
Reported complete (DPWH)
View all 27 projects →

4. Implementation

Contract Amount

₱1,000,000.00

Progress

Reported complete (DPWH)

Start Date

March 4, 2021

Target End

April 19, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.