Construction of Slope Protection Structure24CH0030

Construction of Slope Protection Structure along Balantacan River, Balantacan to Sta. Teresa 2nd, Lubao, Pampanga

Construction of Slope Protection Structure along Balantacan River, Balantacan to Sta. Teresa 2nd, Lubao, Pampanga is a DPWH-tracked public work in LUBAO (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱41,852,777.94. Status: Reported complete (DPWH). Contractor on record: V TRILLANA BUILDERS & TRADING / RADIANS BUILDERS AND SUPPLY CORP. Figures trace to sumbong.

LUBAO (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Pampanga River, Apalit, Pampanga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0000847

₱2,734,358.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008252

₱1,392,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0000848

₱249,126.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0004196

₱246,231.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0008253

₱129,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱41.9M total · 1 flags

4. Implementation

Contract Amount

₱41,852,777.94

Progress

Reported complete (DPWH)

Start Date

February 19, 2024

Target End

August 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.