Construction of Revetment23KK0072

Construction of Revetment at Tagbocboc Bridge (Abutment A and B), Talisayan, Misamis Oriental

Construction of Revetment at Tagbocboc Bridge (Abutment A and B), Talisayan, Misamis Oriental is a DPWH-tracked public work in TALISAYAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X. Reported contract value: ₱72,375,000.00. Status: Reported complete (DPWH). Contractor on record: RITCHE-NATHALIE BUILDERS & GEN MERCHANDISE. Figures trace to sumbong.

TALISAYAN (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project, Upstream of Dangoan Bridge 1, Medina, Misamis Oriental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Misamis Oriental 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

30 projects · ₱2.1B total · 0 flags

4. Implementation

Contract Amount

₱72,375,000.00

Progress

Reported complete (DPWH)

Start Date

April 25, 2023

Target End

January 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.