Buildings and Facilities23CA0024

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM -BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - CONSTRUCTION (COMPLETION) OF DPWH BATAAN 1ST DEO BUILDING, ROMAN EXPRESSWAY, MULAWIN, ORANI, BATAANORANI, BATAAN

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM -BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - CONSTRUCTION (COMPLETION) OF DPWH BATAAN 1ST DEO BUILDING, ROMAN EXPRESSWAY, MULAWIN, ORANI, BATAANORANI, BATAAN is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱92,713,338.75. Status: Past target date (DPWH On-Going). Contractor on record: 88 BUILDERS CONST. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project along Orani River, Orani, Bataan (Phase III-A1)
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bataan 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

39 projects · ₱881.8M total · 0 flags

4. Implementation

Contract Amount

₱92,713,338.75

Progress

Past target date (DPWH On-Going)

Start Date

March 7, 2023

Target End

January 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.