Roads18GI0061

PREVENTIVE MAINTENANCE OF ROAD: CONCRETE REBLOCKING - CABATUAN - NEW LUCENA - BANGA BANTE RD, K0034+(-726) - K0034+(-612.4), K0034+(-726) - K0034+(-604.6), K0034+(-573) - K0034+(-496), K0034+012 - K0034+115.3, K0034+079.5 - K0034+106.4, K0034+137.8 - K003

PREVENTIVE MAINTENANCE OF ROAD: CONCRETE REBLOCKING - CABATUAN - NEW LUCENA - BANGA BANTE RD, K0034+(-726) - K0034+(-612.4), K0034+(-726) - K0034+(-604.6), K0034+(-573) - K0034+(-496), K0034+012 - K0034+115.3, K0034+079.5 - K0034+106.4, K0034+137.8 - K003 is a DPWH-tracked public work in Iloilo 4th DEO, Region VI. Reported contract value: ₱11,495,388.03. Status: Reported complete (DPWH). Contractor on record: CABILAUAN CONST AND SUPPLY. Figures trace to dpwh.

Iloilo 4th DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Aganan Flood Control Project (Jaro-Aganan River), Brgy. 14, San Miguel, Iloilo
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROI-18-0007875

₱79,883.00 · FY2018

Released to Regional Office - I (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱11,495,388.03

Progress

Reported complete (DPWH)

Start Date

May 28, 2018

Target End

October 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.