Flood Control and Drainage18KF0039

CONSTRUCTION OF SLOPE PROTECTION ALONG KAWIT BRIDGE, (UPSTREAM) INCLUDING ROW, LINAMON-ZAMBOANGA ROAD, KAUSWAGAN, LANAO DEL NORTE

CONSTRUCTION OF SLOPE PROTECTION ALONG KAWIT BRIDGE, (UPSTREAM) INCLUDING ROW, LINAMON-ZAMBOANGA ROAD, KAUSWAGAN, LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 1st DEO, Region X. Reported contract value: ₱26,247,550.71. Status: Reported complete (DPWH). Contractor on record: N B SALBO CONST 6091. Figures trace to dpwh.

Lanao del Norte 1st DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱26,247,550.71

Progress

Reported complete (DPWH)

Start Date

February 20, 2018

Target End

August 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.