Buildings and Facilities22HA0128

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. DAMPAS, TAGBILARAN CITY, BOHOL

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. DAMPAS, TAGBILARAN CITY, BOHOL is a DPWH-tracked public work in Bohol 1st DEO, Region VII. Reported contract value: ₱1,977,000.70. Status: Reported complete (DPWH). Contractor on record: HUSAIN CONST AND SUPPLY CO 42783. Figures trace to dpwh.

Bohol 1st DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control / Drainage Projects, Tagbilaran City, Bohol
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Bohol 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 42783

40 projects · ₱251.1M total · 0 flags

4. Implementation

Contract Amount

₱1,977,000.70

Progress

Reported complete (DPWH)

Start Date

May 25, 2022

Target End

September 22, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.