Roads23PB0028

- ASSET PRESERVATION-CONSTRUCTION/ UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-CONSTRUCTION OF DRAINAGE STRUCTURE ALOAD ROAD-CONNER-KABUGAO RD- K0572+200-K0572+285

- ASSET PRESERVATION-CONSTRUCTION/ UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-CONSTRUCTION OF DRAINAGE STRUCTURE ALOAD ROAD-CONNER-KABUGAO RD- K0572+200-K0572+285 is a DPWH-tracked public work in Apayao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱1,200,500.00. Status: Reported complete (DPWH). Contractor on record: ISAGA BUILDERS. Figures trace to dpwh.

Apayao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2023 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱1,166,429 · ISAGA BUILDERS

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2022-07-22 → 2025-04-06

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: - ASSET PRESERVATION-CONSTRUCTION/ UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-SECONDARY ROADS-CONSTRUCTION OF DRAINAGE STRUCTURE ALOAD ROAD-CONNER-KABUGAO RD- K0572+200-K0572+285

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Badduat River Flood Control along Apayao-Abulug River Basin, Sta. 83 + 292 - Sta. 83 + 532, Kabugao, Apayao
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Apayao 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Projects

₱1,166,428.67 · ISAGA BUILDERS

Award / contract ref: 23PB0028

Possible match · 70%

Construction of Gate Balzain Elementary School

₱173,984.40 · ISAGA BUILDERS

Contractor

B

22 projects · ₱142.6M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF BARREN RIVER (UPSTREAM) FLOOD CONTROL, BRGY. TALIFUGO, CONNER, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2020₱19.0M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, APAYAO-ILOCOS NORTE RD - K0609+175 - K0609+206, K0611+015 - K0611+036, K0611+335 - K0611+359

Apayao 1st DEO, Cordillera Administrative Region

2023₱16.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, APAYAO-ILOCOS NORTE RD - K0613 + 012 - K0613 + 300

Apayao 1st DEO, Cordillera Administrative Region

2024₱14.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM- REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, APAYAO-ILOCOS NORTE RD - K0623 + 742 - K0623 + 962

Apayao 1st DEO, Cordillera Administrative Region

2024₱14.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, ABBUT-CONNER RD - K0553+041 - K0553+366, CONNER, APAYAO

Apayao 1st DEO, Cordillera Administrative Region

2022₱9.8M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, CONNER-KABUGAO RD - K0591 + 580 - K0591 + 620

Apayao 1st DEO, Cordillera Administrative Region

2024₱9.8M
Reported complete (DPWH)
View all 22 projects →

4. Implementation

Contract Amount

₱1,200,500.00

Progress

Reported complete (DPWH)

Start Date

May 4, 2023

Target End

July 22, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Cordillera Administrative Region (CAR)ApayaoConnerCalafug
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.