Water Provision and Storage21FI0057

CLUSTER IV - CONSTRUCTION OF RAINWATER COLLECTOR (RWCS) AT MOBO, MASBATE; A. TUGBO INTEGRATED SCHOOL (ANNEX CAMPUS), MOBO, MASBATE; B. TUGBO INTEGRATED SCHOOL (MAIN CAMPUS), MOBO, MASBATE; C. DACU ES, MOBO, MASBATE

CLUSTER IV - CONSTRUCTION OF RAINWATER COLLECTOR (RWCS) AT MOBO, MASBATE; A. TUGBO INTEGRATED SCHOOL (ANNEX CAMPUS), MOBO, MASBATE; B. TUGBO INTEGRATED SCHOOL (MAIN CAMPUS), MOBO, MASBATE; C. DACU ES, MOBO, MASBATE is a DPWH-tracked public work in Masbate 2nd DEO, Region V. Reported contract value: ₱924,949.84. Status: Reported complete (DPWH). Contractor on record: 3R3M CONST AND SUPPLY CORP FORMERLY: 3R3M CONST AND SUPPLY. Figures trace to dpwh.

Masbate 2nd DEO, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2021 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱4,238,928 · SHALJOMAR CONSTRUCTION & SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2022-08-02 → 2025-10-24

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CLUSTER IV - CONSTRUCTION OF RAINWATER COLLECTOR (RWCS) AT MOBO, MASBATE; A. TUGBO INTEGRATED SCHOOL (ANNEX CAMPUS), MOBO, MASBATE; B. TUGBO INTEGRATED SCHOOL (MAIN CAMPUS), MOBO, MASBATE; C. DACU ES, MOBO, MASBATE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Lumbang River Flood Control Masbate City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Masbate 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

20FI0057

₱4,238,927.96 · SHALJOMAR CONSTRUCTION & SUPPLY

Contractor

B

71 projects · ₱974.4M total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BITO RIVER (DOWNSTREAM), BRGY. CORBADA, SAN FERNANDO, MASBATE.

Masbate 1st DEO, Region V

2024₱49.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

Construction of Dimasalang Flood Control, Barangay G. Aliño, Dimasalang, Masbate

DIMASALANG (MASBATE), MASBATE, Region V

2024₱48.9M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF FLOOD MITIGATION STRUCTURE- CONSTRUCTION OF CANOMAY FLOOD CONTROL, BARANGAY CANOMAY, DIMASALANG, MASBATE

Masbate 3rd DEO, Region V

2024₱48.9M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORE PROTECTION STRUCTURE, LAGUNDI, BARANGAY BURGOS, BATUAN, MASBATE.

Masbate 1st DEO, Region V

2025₱47.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - JCT. TAWAD-BALUD ROAD (S00023MT) K0039+670 - K0039+812, K0039+882 - K0040+019

Masbate 2nd DEO, Region V

2025₱38.4M
Past target date (DPWH On-Going)
No sat.

OO1: NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- SECONDARY ROADS, BUENAVISTA- KAWAYAN RD- K0050+729- K0051+400

Masbate 3rd DEO, Region V

2024₱34.2M
Reported complete (DPWH)
View all 71 projects →

4. Implementation

Contract Amount

₱924,949.84

Progress

Reported complete (DPWH)

Start Date

September 28, 2022

Target End

November 6, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)MasbateMoboDacu
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.