Roads25CF0034

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BONGABON, NUEVA ECIJA

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BONGABON, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱9,672,547.90. Status: Reported complete (DPWH). Contractor on record: JERRY R SANTIAGO CONST CORP FORMERLY: JERRY SANTIAGO CONST 18453. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Pampanga River, Barangay Calaba, San Isidro, Nueva Ecija
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Nueva Ecija 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 18453

55 projects · ₱1.4B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/IMPROVEMENT/REHABILITATION/COMPLETION OF VARIOUS MULTI-PURPOSE BUILDINGS (COVERED COURT, BRGY. HALL, EVACUATION CENTER), CALAPAN CITY, ORIENTAL MINDORO

Mindoro Oriental DEO, Region IV-B

2022₱131.7M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - STA. ROSA - TARLAC RD - K0108 + (-881) - K0108 + (-803), K0111 + 100 - K0111 + 832, K0112 + 576.50 - K0113 + 082, K0116 + 000 - K0117 + 724

Nueva Ecija 2nd DEO, Region III

2024₱89.6M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS NUEVA ECIJA - AURORA RD. - K0131+007-K0131+843, K0132+066-K0133+000, K0133+233-K0134+500, K0135+835-K0136+461, K0137+900-K0138+144, K0139+2

Nueva Ecija 2nd DEO, Region III

2023₱86.8M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - NUEVA ECIJA - AURORA RD - K0129+543-K0129+743, K0129+743-K0129+995, K0130+000-K0131+000, K0131+700-K0131+997.50, K0132+000-K0132+11

Nueva Ecija 2nd DEO, Region III

2024₱86.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF ROAD NET ALONG LRR/SF TO MOLAVE, PHILIPPINE ARMY, FORT MAGSAYSAY, PALAYAN CITY, NUEVA ECIJA

Nueva Ecija 2nd DEO, Region III

2020₱81.2M
Reported complete (DPWH)
No sat.

CONCRETING OF ROADS, CALAPAN CITY, ORIENTAL MINDORO

Mindoro Oriental DEO, Region IV-B

2022₱72.5M
Reported complete (DPWH)
View all 55 projects →

4. Implementation

Contract Amount

₱9,672,547.90

Progress

Reported complete (DPWH)

Start Date

February 14, 2025

Target End

April 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.