Flood Control and Drainage15MB0177

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS, BUAYAN-MALUNGON RIVER BASINS, GENERAL SANTOS CITY, SOUTH COTABATO 1ST LD

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS, BUAYAN-MALUNGON RIVER BASINS, GENERAL SANTOS CITY, SOUTH COTABATO 1ST LD is a DPWH-tracked public work in South Cotabato 1st DEO, Region XII. Reported contract value: ₱36,647,865.60. Status: Reported complete (DPWH). Contractor on record: DELLOSA DESIGN BUILDERS CORP FORMERLY:DELLOSA DESIGN-BUILD SERVICES. Figures trace to dpwh.

South Cotabato 1st DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱13,768,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Carpenter Hill Flood Control and drainage structures, Barangay Carpenter Hill, Koronadal City, South Cotabato
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0004542

₱515,000.00 · FY2016

Released to Samar National Pilot Opportunity School of AgricuP (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

22 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱36,647,865.60

Progress

Reported complete (DPWH)

Start Date

April 10, 2016

Target End

October 21, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.