Construction of Revetment23NB0019

Construction of Revetment along Agusan River Basin, Esperanza Section, Agusan del Sur

Construction of Revetment along Agusan River Basin, Esperanza Section, Agusan del Sur is a DPWH-tracked public work in ESPERANZA (AGUSAN DEL SUR), AGUSAN DEL SUR, Region XIII. Reported contract value: ₱53,074,962.28. Status: Reported complete (DPWH). Contractor on record: ADFIL CORP. Figures trace to sumbong.

ESPERANZA (AGUSAN DEL SUR), AGUSAN DEL SUR, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Mitigation along Adlayan River Bank (Downstream) San Francisco, Agusan Del Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Agusan del Sur 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

215 projects · ₱22.1B total · 2 flags

4. Implementation

Contract Amount

₱53,074,962.28

Progress

Reported complete (DPWH)

Start Date

March 31, 2023

Target End

January 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.