Flood Control and Drainage19MA0010

CONSTRUCTION OF RIVERBANK PROTECTION (REVETMENT) ALONG TAMONTAKA RIVER (TAMONTAKA 1 TO TAMONTAKA 2 SECTION, PHASE IV), COTABATO CITY

CONSTRUCTION OF RIVERBANK PROTECTION (REVETMENT) ALONG TAMONTAKA RIVER (TAMONTAKA 1 TO TAMONTAKA 2 SECTION, PHASE IV), COTABATO CITY is a DPWH-tracked public work in Cotabato City DEO, Region XII. Reported contract value: ₱4,741,118.76. Status: Reported complete (DPWH). Contractor on record: ARS CONST AND SUPPLY. Figures trace to dpwh.

Cotabato City DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,741,118.76

Progress

Reported complete (DPWH)

Start Date

August 1, 2019

Target End

September 26, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.