Bridges23K00198

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CAGAYAN DE ORO DIVERSION ROAD, (JCT. BALUBAL SAYRE HIGHWAY-PUEBLO DE ORO, CDO-OLD AIRPORT ROAD DIVERSION ROAD (PUEBLO DE ORO/JCT. CDO-OLD AIRPORT ROAD) PHASE II, PACKAGE 17, CAGAYAN DE ORO CITY

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, CAGAYAN DE ORO DIVERSION ROAD, (JCT. BALUBAL SAYRE HIGHWAY-PUEBLO DE ORO, CDO-OLD AIRPORT ROAD DIVERSION ROAD (PUEBLO DE ORO/JCT. CDO-OLD AIRPORT ROAD) PHASE II, PACKAGE 17, CAGAYAN DE ORO CITY is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱95,244,276.10. Status: Reported complete (DPWH). Contractor on record: GICAR CONST INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱95,244,276.10

Progress

Reported complete (DPWH)

Start Date

May 16, 2023

Target End

March 10, 2024

5. Audit