Published flags in Santa Cruz
10 published flags on records linked to Santa Cruz and the LGUs under it. A flag is an automated anomaly that reviewers checked before publishing: a question worth asking, not a finding of wrongdoing.
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Mitigation Structure, Bayto River (Upstream North Approach), Sta. Cruz, ZambalesDPWH project · contractor Big Bertha Const & Development
- C7 · High Concurrent Workload for One ContractorNorthern BuildersContractor (applies to all its work) · contractor Northern Builders
- C5 · Pattern Consistent with Contract SplittingConstruction of Gama River Slope Protection/ Flood Control Structure Phase 3, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C5 · Pattern Consistent with Contract SplittingConstruction of Gama River Slope Protection/ Flood Control Structure Phase 2, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C5 · Pattern Consistent with Contract SplittingConstruction of Guinabon Flood Control at Nayum River, Brgy. Guinabon, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C5 · Pattern Consistent with Contract SplittingConstruction of Guisguis Flood Control at Nayum River, Brgy. Guisguis, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C4 · Schedule / Date InconsistenciesConstruction of Gama River Slope Protection/ Flood Control Structure Phase 3, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C4 · Schedule / Date InconsistenciesConstruction of Gama River Slope Protection/ Flood Control Structure Phase 2, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C4 · Schedule / Date InconsistenciesConstruction of Guisguis Flood Control at Nayum River, Brgy. Guisguis, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
- C4 · Schedule / Date InconsistenciesConstruction of Guinabon Flood Control at Nayum River, Brgy. Guinabon, Sta. Cruz, ZambalesDPWH project · contractor E R Dela Cruz Const & Supply
Named parties may reply or request a correction. See the methodology.