19 published flags on records linked to Dolores and the LGUs under it. A flag is an automated anomaly that reviewers checked before publishing: a question worth asking, not a finding of wrongdoing.
- C2 · Awards Very Close to the Budget CeilingConstruction of Cardona - Isit Flood Control, Barangay Cardona, Dolores, AbraDPWH project · contractor St Timothy Const Corp
- C2 · Awards Very Close to the Budget CeilingConstruction of Bayaan Flood Control, Barangay Bayaan, Dolores, AbraDPWH project · contractor St Timothy Const Corp
- C1 · Contractor Concentration (Flood Control)Mg Samidan ConstContractor (applies to all its work) · contractor Mg Samidan Const
- C1 · Contractor Concentration (Flood Control)Mg Samidan ConstContractor (applies to all its work) · contractor Mg Samidan Const
- C7 · High Concurrent Workload for One ContractorSt Timothy Const CorpContractor (applies to all its work) · contractor St Timothy Const Corp
- C7 · High Concurrent Workload for One ContractorMg Samidan ConstContractor (applies to all its work) · contractor Mg Samidan Const
- C5 · Pattern Consistent with Contract SplittingConstruction of Cardona - Isit Flood Control, Barangay Cardona, Dolores, AbraDPWH project · contractor St Timothy Const Corp
- C5 · Pattern Consistent with Contract SplittingConstruction of Bayaan Flood Control, Barangay Bayaan, Dolores, AbraDPWH project · contractor St Timothy Const Corp
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Cardona Flood Control Structure, Barangay Cardona, Dolores, AbraDPWH project · contractor Mg Samidan Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure, Barangay Cardona, Dolores, AbraDPWH project · contractor St Timothy Const Corp
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure Along Abra Major River Basin, Barangay Lagben, Lagangilang, AbraDPWH project · contractor Mg Samidan Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure Along Abra Major River Basin, Barangay Nagtupacan, Dolores, AbraDPWH project · contractor Mg Samidan Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Paga Flood Control, Dolores, AbraDPWH project · contractor Mg Samidan Const
- C4 · Schedule / Date InconsistenciesConstruction of Paga Flood Control, Dolores, AbraDPWH project · contractor Mg Samidan Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure Along Abra Major River Basin, Paga, Cardona, Dolores, AbraDPWH project · contractor Mg Samidan Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Isit Flood Control, Dolores, AbraDPWH project · contractor Mg Samidan Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Structure Along Abra Major River Basin (Phase Ii), Bagalay, Tayum, AbraDPWH project · contractor Mg Samidan Const
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control Structure, Barangay Isit, Dolores, AbraDPWH project · contractor Mg Samidan Const
- C2 · Awards Very Close to the Budget CeilingConstruction of Cardona Flood Control Structure, Barangay Cardona, Dolores, AbraDPWH project · contractor Mg Samidan Const
Named parties may reply or request a correction. See the methodology.