Barangay
Mudeng
Mudeng, La Paz, Abra, Cordillera Administrative Region (CAR). Rural. Population 1,300 (2024 POPCEN).
PSGC 1400108008 · Source: PSA, PSGC 3Q 2026 Publication Datafile
Public records linked to Mudeng
Counts include this barangay and every LGU under it. Each record carries how it was linked and a confidence level; figures are as recorded by the source and exclude single amounts of ₱10B+ held for verification. They are not findings.
DPWH infrastructure projects
Contracts on the DPWH Transparency portal, placed by coordinates first. Source: DPWH Transparency portal
38 records · ₱1,788,306,514.33
- Construction of University of Abra School Building La Paz Campus, La Paz, Abra₱96,500,000.00 · 2022 · medium confidence (project coordinates inside the barangay boundary)
- Oo2: Protect Lives and Properties Against Major Floods, Construction/ Rehabilitation of Flood Mitigation Facilities Within Major River Basins and Principal River, Construction of Flood Control Structure Along Abra River Basin (Phase Ii), Calaba, Bangued,₱96,497,672.25 · 2023 · medium confidence (project coordinates inside the barangay boundary)
- Construction (Completion) of Convention Center, La Paz, Abra₱96,496,777.30 · 2022 · medium confidence (project coordinates inside the barangay boundary)
- Construction of Flood Control Structure, Barangay Mudeng, La Paz, Abra₱95,238,758.44 · 2022 · medium confidence (project coordinates inside the barangay boundary)
- Construction of Multi-Purpose Building, University of Abra La Paz Campus, Barangay Mudeng, La Paz, Abra₱93,122,228.48 · 2024 · medium confidence (project coordinates inside the barangay boundary)
- Construction of Soot Flood Control Structure, La Paz, Abra₱92,109,279.07 · 2022 · medium confidence (project coordinates inside the barangay boundary)
How linked: 38 by project coordinates inside the barangay boundary.
Contracts this LGU awarded (PhilGEPS)
PhilGEPS awards where the procuring entity is this LGU. Source: PhilGEPS award notices
Not yet linked to Mudeng itself. This shows the municipality figure for La Paz.
1 record · ₱613,235,096.19
- Municipality of La Paz, Abra₱613,235,096.19 · high confidence (the LGU itself is the buyer)
How linked: 1 by the LGU itself is the buyer.
PhilGEPS awards delivered here (all agencies)
Awards by any agency whose area of delivery is this province. PhilGEPS records delivery areas at province level only. Source: PhilGEPS award notices
Not yet linked to Mudeng itself. This shows the province figure for Abra.
8,355 records · ₱100,465,305,547.71
8,328 placed at Abra level itself; the rest in LGUs under it.
- Abra₱100,465,305,547.71 · 8,328 awards · high confidence (area of delivery is this province only)
- Abra, Agusan del Norte₱67,685,421.80 · 10 awards · low confidence (area of delivery lists several provinces)
- Abra, Albay, Cotabato, Negros Occidental, Nueva Ecija₱9,712,257.84 · 1 awards · low confidence (area of delivery lists several provinces)
- Abra, Benguet, Ilocos Norte, Ilocos Sur, La Union₱4,869,600.00 · 6 awards · low confidence (area of delivery lists several provinces)
- Abra, Benguet, Ilocos Norte, Ilocos Sur, La Union, Mountain Province₱2,793,144.00 · 5 awards · low confidence (area of delivery lists several provinces)
- Abra, Agusan del Norte, Agusan del Sur₱585,000.00 · 4 awards · low confidence (area of delivery lists several provinces)
How linked: 8,328 by area of delivery is this province only; 27 by area of delivery lists several provinces.
Local Government Support Fund releases
DBM LGSF project releases by province, city/municipality and barangay. Source: DBM COMPASS
Not yet linked to Mudeng itself. This shows the municipality figure for La Paz.
7 records · ₱76,854,227.00
4 placed at La Paz level itself; the rest in LGUs under it.
- Lgsf_gef₱30,000,000.00 · 2026 · high confidence (location columns in the DBM release)
- Construction of Bridge in Barangay Udangan, La Paz₱20,000,000.00 · 2026 · high confidence (location columns in the DBM release)
- Rehabilitation of Multi-Purpose Building in La Paz, Abra₱10,000,000.00 · 2024 · high confidence (location columns in the DBM release)
- Lgsf_gef₱5,153,720.00 · 2022 · high confidence (location columns in the DBM release)
- Lgsf_gef₱3,900,169.00 · 2026 · high confidence (location columns in the DBM release)
- Lgsf_gef₱3,900,169.00 · 2026 · high confidence (location columns in the DBM release)
How linked: 7 by location columns in the DBM release.
GAA budget lines naming this place
General Appropriations Act lines whose text ends in this city/municipality and province. Source: DBM General Appropriations Act
18 records · ₱878,500,000.00
- Construction of Flood Control Structure Along Abra Major River Basin, Barangay Mudeng, La Paz, Abra₱100,000,000.00 · 2023 · medium confidence (GAA line text names the place)
- Construction of Flood Control Structure, Barangay Mudeng, La Paz, Abra₱100,000,000.00 · 2022 · medium confidence (GAA line text names the place)
- Construction of Flood Control Structure, Coribot, Barangay Mudeng, La Paz, Abra₱100,000,000.00 · 2022 · medium confidence (GAA line text names the place)
- Construction of Multi - Purpose Building, University of Abra La Paz Campus, Barangay Mudeng, La Paz, Abra₱100,000,000.00 · 2024 · medium confidence (GAA line text names the place)
- Construction (Completion) of Multi-Purpose Building, Abra Central Market, Barangay Mudeng, La Paz, Abra₱50,000,000.00 · 2022 · medium confidence (GAA line text names the place)
- Construction of Abra Central Market, Brgy. Mudeng, La Paz, Abra₱50,000,000.00 · 2021 · medium confidence (GAA line text names the place)
How linked: 18 by GAA line text names the place.
COA annual audit reports
Not yet linked: the COA reports loaded so far cover national agencies only. LGU audit reports are published at coa.gov.ph.
Published anomaly flags
Patterns in the linked records that reviewers checked and published. A flag is a question worth asking, not a finding of wrongdoing.
- Awards Very Close to the Budget CeilingConstruction of Mudeng Flood Control Structure (Phase 3), Barangay Mudeng, La Paz, AbraContractor: 739 Builders
- Awards Very Close to the Budget CeilingConstruction of Soot Flood Control Structure (Phase 2), Barangay Mudeng, La Paz, AbraContractor: St Timothy Const Corp
- Contractor Concentration (Flood Control)Mg Samidan ConstContractor: Mg Samidan Const
- Contractor Concentration (Flood Control)Mg Samidan ConstContractor: Mg Samidan Const
- Pattern Consistent with Contract SplittingConstruction of Mudeng Flood Control Structure (Phase 3), Barangay Mudeng, La Paz, AbraContractor: 739 Builders
- High Concurrent Workload for One ContractorMg Samidan ConstContractor: Mg Samidan Const
Contractors on linked DPWH projects
All 14 contractors on DPWH projects linked to Mudeng and the LGUs under it. Click a column to sort.
| 739 Builders | 12 | ₱805,594,798.60 | 2 |
| Phesco INC 145 | 6 | ₱258,069,673.22 | 0 |
| St Timothy Const CORP | 3 | ₱147,995,000.00 | 5 |
| North Tech Builders And Const Supply | 1 | ₱96,497,672.25 | 0 |
| Mg Samidan Const / Rm30 Psg Const CORP | 1 | ₱95,238,758.44 | 2 |
| Katha Builders | 2 | ₱87,519,920.00 | 0 |
| F B Bantales Engineering Const | 1 | ₱77,099,835.41 | 0 |
| R A Fanglayan Raf Gen Const INC Formerly:Raf Gen Const | 3 | ₱56,474,439.39 | 0 |
| Mg Samidan Const | 1 | ₱48,997,500.00 | 4 |
| Viking Const | 1 | ₱44,117,726.98 | 0 |
| A D Marrero Gen Const | 3 | ₱33,605,885.96 | 0 |
| Sembri Const | 1 | ₱19,798,000.00 | 0 |
| Balligi Const Development CORP Formerly:Balligi Const | 2 | ₱12,714,285.35 | 0 |
| Tuquer Builders | 1 | ₱4,583,018.73 | 0 |
Costs as recorded by DPWH; single amounts of ₱10B+ are held for verification and excluded. Flags count published automated anomalies on this contractor's projects or awards here, plus flags on the contractor itself; they are not findings.

Share this page
The card shows the public record facts and a QR code back to this page.
QR codes for Mudeng
Print these or the flyer and post them in your barangay hall, market or school. Both use high error correction, so they still scan when partly worn.